Applied Digital (NASDAQ: APLD) signed an 18-year lease for 150 megawatts of critical IT capacity with an unnamed investment-grade hyperscaler. The $5.4 billion base-term value normalizes to about $300 million a year and $2.0 million per critical MW-year—roughly 20% above two previously disclosed large leases on the same simple basis. That is meaningful pricing evidence, but it is not current revenue: delivery is expected to begin in the first half of 2028, and the company still needs project financing to convert contracted capacity into operating cash flow.
Research cutoff: November 23, 2026, 11:10 a.m. ET. We use Applied Digital’s official releases and its latest Form 10-Q. The new lease release does not name the campus or customer, and the separate $300 million bridge facility is for Delta Forge 1. We do not assume the two announcements describe the same project.
Three findings
- The new lease implies $300 million of simple annual base contract value, or $2.0 million per critical MW-year. That is not a GAAP revenue forecast and excludes the effects of commencement, escalation, pass-through items and operating costs.
- The $12.7 billion 33-year figure depends on renewal options. The $5.4 billion base term is the non-option comparison, but revenue still waits for delivery and lease commencement expected in first-half 2028.
- The $300 million Delta Forge 1 facility is a 364-day delayed-draw bridge, not full construction funding. Applied Digital explicitly expects additional financing for completion.
The contract math improves; the cash timing does not disappear
| Lease comparison | Critical IT load | Base term / value | Simple value per MW-year |
|---|---|---|---|
| New unnamed hyperscaler | 150 MW | 18 years / $5.4B | $2.000M |
| Delta Forge 1 or Polaris Forge 3 (each) | 300 MW | 15 years / $7.5B | $1.667M |
| Delta Forge 2 | 210 MW | 15 years / $5.2B | $1.651M |
The new contract’s simple per-MW figure is 20.0% above the Delta Forge 1/Polaris Forge 3 comparison and 21.2% above Delta Forge 2. This is consistent with management’s statement that pricing is higher. It is not enough to calculate a rent rate, NOI margin or cash yield because the release does not disclose power pass-throughs, escalation schedules, operating expenses or the precise phased commencement.
Applied Digital said delivery is currently expected in the first half of 2028 and remains subject to development milestones, utility arrangements and regulatory approvals. Until the capacity is delivered and the lease commences, the $5.4 billion is contracted value rather than recognized revenue or cash on the balance sheet. The larger $12.7 billion number assumes every renewal is exercised over 33 years and should not be treated as firm current backlog.
The portfolio is larger, but the denominator matters
The company now reports more than $41 billion of contracted base-term revenue, about $100 billion including all renewals, more than 1.6 GW of contracted critical IT load and 2.2 GW of grid-connected peak power. It says approximately 75% of total contracted base-term lease revenue is attributable to investment-grade tenants. These are company-defined contract and power measures, not current recognized revenue or cash.
That distinction resembles the project-value versus supplier-revenue gap discussed in our Bloom Energy/AEP/Google project analysis. Large infrastructure totals can be economically important without becoming near-term reported revenue for every participant.
The $300 million bridge is temporary funding
Fifteen minutes before the lease release, Applied Digital announced a separate $300 million senior secured delayed-draw term loan for Delta Forge 1. The facility matures in 364 days and bears interest at SOFR plus 300 basis points. Draws depend on construction milestones, a state-commission electrical-rate approval, lender consents and financial covenants. The company can prepay without premium.
This is a closed financing facility, but not the same as $300 million already drawn or enough cash to complete the campus. Applied Digital said it expects additional project financing for completion. It expects remaining project financing for Delta Forge 1 and Polaris Forge 3 in the first calendar quarter of 2027, and for Delta Forge 2 in the second calendar quarter of 2027. Using the New York Fed’s 3.92% SOFR reading for November 20 as a reference, a fully drawn one-year balance would carry a simple annualized interest cost of about $20.8 million before fees; actual cost will depend on draw timing and future SOFR.
The latest balance sheet shows why financing remains central
| August 31, 2026 / fiscal Q1 | Reported value | Interpretation |
|---|---|---|
| Unrestricted cash | $2.950B | Liquidity before restricted project cash |
| Restricted cash | $728M | Not freely interchangeable with unrestricted cash |
| Gross debt | About $6.377B | Current plus long-term debt before the new bridge |
| Property and equipment purchases | $2.075B in the quarter | Expansion remains capital intensive |
| Operating / investing / financing cash flow | +$63.9M / −$2.083B / +$1.543B | External capital still funds most growth |
| Fiscal Q1 revenue / consolidated net loss | $341.9M / $184.1M loss | Contracted capacity is scaling faster than current earnings |
The company’s $5 billion Macquarie programmatic equity partnership is a funding framework, not $5 billion of unrestricted cash already available. It depends on project conditions, additional investments and definitive documents. The broader lesson also appears in our CoreWeave debt-and-cash-flow review: long-duration contracted demand can coexist with short-duration financing and refinancing risk.
Dilution and asset-level claims remain part of the return
Common shares outstanding increased from 287.9 million on May 31 to 297.1 million on August 31, a 3.2% rise. The 10-Q also reported that remaining Series G preferred shares converted into 5.2 million common shares after quarter-end. At August 31, 28.1 million warrants were outstanding with an $8.61 average exercise price, alongside 7.8 million unvested restricted stock units and 7.5 million performance stock units. These instruments should not all be mechanically added to the current diluted share count, but they show that per-share value depends on more than contract totals.
Preferred and noncontrolling interests at project entities also have economic claims ahead of or alongside common equity. The lease improves the evidence for demand and simple contract value per MW. It does not yet prove construction completion, lease commencement, margin, refinancing or common-share cash yield.
What would change the conclusion
- A filed contract or 8-K that identifies the campus, commencement schedule, escalation and termination protections.
- Closed long-term project financing that replaces the 364-day bridge on sustainable terms.
- Evidence that construction, utility and regulatory milestones remain on schedule for first-half 2028 delivery.
- Reported base rent and cash collection that convert contract value into recurring revenue and operating cash flow.
- Per-share growth that outruns new common issuance, warrants, equity awards and preferred claims.
We do not maintain a comparable current APLD base target for this event, and no sufficiently verified post-announcement analyst target set was available at the cutoff. The 20% AHNIM-versus-consensus gap test is therefore not applicable.
Sources and original documents
- Applied Digital 150 MW lease release, November 23, 2026
- Applied Digital $300 million senior secured delayed-draw facility release, November 23, 2026
- Applied Digital Form 10-Q for the quarter ended August 31, 2026
- Applied Digital fiscal Q1 2027 earnings release
- Federal Reserve Bank of New York, SOFR reference rates, November 20, 2026 observation used for the illustration
For information and education only; not investment advice. Contract value, recognized revenue and cash flow are different measures.